Awards and Recognitions
Employee News
Featured Projects
Memberships and Affiliations
Featured Projects

MSR-FSR New Cleanroom Laundry Facility

Project Manager: Mike McQuillin
Project Engineer: Steve Klein Project Superintendent: Rick Wilson

The MSR-FSR Cleanroom Laundry project was a Design-Build-Construct project. Terry Wilson, the TriQuint Facility Manager, forwarded our information to MSR after we successfully completed three consecutive Design-Build-Construct projects at TriQuint. We partnered with LRS Architects and designed the Cleanroom envelope and the equipment layout.

A cleanroom laundry has several requirements beyond a normal laundry. The process needs to include a DI water system for the wash cycles, a steam boiler for the dryers and for making hot DI water, and a class 10 certified cleanroom. We designed the class 10 cleanroom to be encapsulated by the return chase with full height walls to eliminate the need for conditioning the entire warehouse space. We then only needed to condition the “clean envelope” around the cleanroom. This was a huge advantage as a cost reduction for our construction budget.

We installed the 400# capacity Washers (see picture above), High Purity Steam Dryers, RODI Skids, Storage Tanks, Natural Gas Boiler, Air Compressor equipment, HVAC Rooftop Units, and all the process piping. The biggest challenge with this project was working with the constraints of a 6000 sf concrete tilt up warehouse that was not pre-facilitated for this type of use. These challenges were overcome during design and we were able to provide and meet a construction budget that was less than 50% of what MSR had received previously from another design team.

Our strategy included assembling a Project Team of subcontractors that had successfully performed the three prior projects at TriQuint. The communication and cohesive work environment created by having an existing relationship with the project team allowed us to complete the project in a mere 16 weeks from receipt of permit.

The project went very well and our customer is very satisfied. We will be starting our next Design-Build-Construct project for MSR by relocating their current semiconductor parts cleaning operation in Gresham, OR to this new facility this Spring.



University of Washington Medical Center H-Wing Renovation Project

As the prime mechanical contractor, BMWC was accountable for all the mechanical work for this $35 million H-Wing renovation project. The project involved upgrading a 60 year old, 150,000 sf building, which included the renovation of five floors. BMWC's $9.5 million subcontract included all of the mechanical, plumbing, HVAC, and controls.  There were very few change orders on this project for our mechanical work based on our extensive pre-planning efforts, attention to the schedule, and our Lean construction techniques. 



Portland International Airport Deicing Collection and Treatment System Enhancement Project

The Portland Airport is increasing its ability to collect and treat the Deicing Chemicals used for the runways and airplanes. The project consists of two 6.5 million gallon concrete storage tanks and one 3 million gallon concrete storage tanks with interconnecting conveyance piping and pump stations to the New Treatment Facility. BMWC's scope of work is the procurement and installation of the pumping and treatment equipment and the associated piping. The piping varies from 72" carbon steel to 1/2" stainless steel. The equipment consists of 62 pumps ranging from 30" centrifugal pumps to 1" positive displacement pumps. The project also has two 35 foot tall by 14 foot diameter stainless steel activated carbon reactors that will aid in the treatment facility.